Grids and permits: why renewables and new industry wait in Spain
Spain has permits for far more wind and solar than it has built, and most new factories can't get a connection. Where the queue jams and how to clear it.
In short
Renewables and new industry wait in Spain because the grid has become the bottleneck. Red Eléctrica's transmission grid holds access permits for 129 GW of wind and solar, far more than is built, while distributors could not serve two-thirds of the roughly 40 GW of demand that asked to connect in 2025 and grid investment has been capped by law at a fraction of GDP. Spain clears the queue by building grids ahead of demand where clean power is spare, giving connections to projects ready to build, charging for capacity that sits unused, and publishing the whole queue every month.
Key points
- Red Eléctrica (February 2026): its transmission grid holds access and connection permits for 129 GW of wind and solar, 16 GW of storage and 19 GW of demand; Spain added more than 40 GW of wind and solar between December 2019 and June 2025.
- aelec: of about 40 GW of demand that asked to connect to distribution grids in 2025, only 12% got access and 66% could not be served.
- Grid investment charged to consumers has been capped at 0.065% of GDP for transmission and 0.13% for distribution; in July 2026 the government added up to €17.9 billion to 2030.
- The 2025–2030 transmission plan, worth €13.6 billion, was still being processed in July 2026.
- The radical-centre answer: build ahead of demand where clean power is spare, ration capacity by readiness and price, and run the queue in public.
In February 2026 Red Eléctrica published something it had never shown before: how much room is left on its transmission grid for new demand. The answer was room at a quarter of its nodes. The same release gave the other side of the ledger. The transmission grid holds access and connection permits for 129 GW of wind and solar, 16 GW of storage and 19 GW of demand. Over the five and a half years to June 2025, according to Ember, Spain actually built more than 40 GW of new wind and solar. The gap between those numbers is the queue, and it is where much of Spain's energy advantage is waiting.
Yesterday we looked at why cheap clean electricity is Spain's productivity edge. The edge turns into factories only if they can plug in, and right now most of them can't.
Two queues, one bottleneck
The generation queue grew in the solar boom. Developers asked for grid access early and cheaply, often for more projects than they could build, because a permit on a good node had value in itself. Royal Decree-law 23/2020 answered with a ladder of deadlines, the hitos administrativos: an admitted authorisation request within six months, environmental approval, a construction permit and the final operating authorisation within five years, with automatic loss of the permit and the guarantee for anyone who misses a rung. That cleared some speculation. In March 2026 Royal Decree-law 7/2026 let holders extend the last deadline to the end of 2030 and froze the clock while court orders are in place.
The demand queue is newer and more worrying. The electricity distributors' association aelec counted about 40 GW of requests to connect new consumption to distribution grids in 2025. Twelve per cent got access. Sixty-six per cent could not be served, and aelec calls the problem structural. Endesa, citing aelec's capacity maps, puts saturated distribution nodes at 83.4%. When the ministry drafted its 2025–2030 grid plan it received requests for 27.7 GW of new demand on the transmission grid, against 2 GW in the plan in force: 13.1 GW for green hydrogen, 9 GW for industry and 3.8 GW for data centres. On the generation side the requests were twice the national plan's target for wind, five times for solar and nine times for storage.
The two queues share a cause. Spain built generation faster than wires. Ember found that between 2019 and 2024 Spain invested 30 cents in grids for every euro in renewables, against a European average of 70 cents. The reason is partly written into law: grid investment that consumers pay for has been capped at 0.065% of GDP for transmission and 0.13% for distribution. The ministry itself says these limits have proved insufficient. In July 2026 the government approved a royal decree that lets up to €17.9 billion more go into grids by 2030, €10.2 billion of it for distribution, allows up to a fifth of distribution investment to be built ahead of demand in saturated areas and penalises companies that repeatedly miss their plans. The CNMC set the return on regulated grid assets at 6.58% for 2026–2031, a full point higher than before and below the more than 7% the utilities asked for. The transmission plan for 2025–2030, worth €13.6 billion against €8.2 billion in the previous one, was still being processed in July 2026.
Meanwhile the cost shows up in the market. Curtailment of renewable output rose to 7.2% between May and July 2025, after the blackout, according to Ember, as the system operator ran more gas plants to hold voltage. Clean power is being thrown away at midday a few kilometres from factories that are told there is no room.
What Abundance and Flyvbjerg add
Ezra Klein and Derek Thompson wrote Abundance about the United States, where they argue that the country has failed to build anything close to the clean-energy infrastructure it needs, and they blame process: reviews and vetoes that protect everything except the ability to build. A review-essay from the Environmental Law Institute pushes back with data that fits Spain well. Full environmental impact statements are a small share of US reviews; what really holds clean energy back is local restrictions and interconnection queues, where the median wait is about five years and only 19% of requests made between 2000 and 2018 were built. Spain shows the same thing. Its permitting has been sped up repeatedly since 2020. Its grid queue is the jam.
Bent Flyvbjerg's How Big Things Get Done adds the delivery lesson. The projects that come in on time are modular: the same small unit built again and again, getting faster each time, like solar farms and wind turbines. A grid planned as one huge, bespoke plan approved every five years behaves like the projects that overrun. A grid built as a stream of standard substations and line upgrades behaves like the solar farms it serves.
A radical-centre way to clear the queue
The left is right that the grid is shared infrastructure. Nobody builds a substation for a factory that does not exist yet, so the state has to plan ahead, and it should plan ahead first in the places with spare clean power, many of them rural regions that host the turbines and want the jobs that come with cheap electricity. The market-liberal tradition is right that scarce capacity needs a price. First-come, first-served rewards whoever filed earliest, and a free reservation invites hoarding. Royal Decree-law 7/2026 has started down this road by replacing guarantees for demand permits with a monthly charge for reserved capacity; by June 2026, 16 consumption projects had given up 1,040 MW on the transmission grid, and Red Eléctrica put that capacity back out to tender at three nodes.
Combined, they make a programme. Raise the investment cap for good and tie it to electrification, with anticipatory building in the saturated, power-rich nodes. Allocate connections by readiness, with land, permits and finance in hand, and charge for capacity that sits idle so that it comes back to the pool. Build grids as a product: standard substation designs, framework contracts, the same crews moving from site to site. Take the European Grids Package of December 2025 at its word, which proposes binding permit deadlines with tacit approval when authorities miss them and an end to first-come, first-served, and write those rules into Spanish law early. The Commission already counts connection queues in at least 16 member states, so Spain can lead here.
And run the whole queue in public. Red Eléctrica's monthly demand map is a good start. The next step is a single register, for generation and demand, that shows every request, its node, its stage and its deadline, updated monthly, so that regions, investors and journalists can see who is waiting, for how long and why. A queue everyone can see gets shorter, and a factory that can find a free node in Extremadura or Aragón on a public map is a factory that gets built.
Questions and answers
Why can't new factories and data centres connect to the grid in Spain?
Because most nodes are full on paper. Distributors' maps compiled by aelec showed 83.4% of distribution nodes saturated, and in 2025 only 12% of about 40 GW of demand requests were granted. Much of the capacity is reserved by projects that have not been built, and grid investment has been capped by law.
How many renewable projects are waiting for the grid in Spain?
Red Eléctrica reported in February 2026 that its transmission grid alone has granted access and connection permits for 129 GW of wind and solar. Ember counts more than 40 GW of wind and solar added between December 2019 and June 2025, so much of the permitted capacity is still on paper.
What are the 'hitos administrativos' for renewable projects?
Royal Decree-law 23/2020 gives projects with grid access a sequence of deadlines, from admitted authorisation request to environmental approval, construction permit and final operating authorisation within five years. Missing one cancels the access permit automatically. Royal Decree-law 7/2026 allowed extensions of the last milestone to the end of 2030.
What does the EU's grids package change?
The European Grids Package of December 2025 proposes binding permit deadlines, with permits considered granted if authorities miss them, and moving away from first-come, first-served grid connections. The Commission says connection queues exist in at least 16 member states.
Sources
- Red Eléctrica publica por primera vez la capacidad de acceso para demanda. Energías Renovables (2026)
- Solo el 12% de las solicitudes de acceso a la red de distribución fueron atendidas. Energías Renovables (2025)
- El Gobierno acelera la electrificación de la economía e incrementa la inversión en redes. Ministry for the Ecological Transition (MITECO) (2026)
- Decoupled: how Spain cut the link between gas and power prices using renewables. Ember (2025)
- European grids. European Commission (2026)
- Abundance: questions about whether permitting reform is really key to the energy transition. Environmental Law Institute (2026)