Climate & energyInterpretation
Almaraz and Spain's nuclear phase-out: an ecopragmatist reading of the extension to 2030
Spain has let Almaraz run until June 2030. What the order says, what it costs, and how to decide the fate of the other six reactors on evidence.
In short
In August 2026 Spain extended the life of the Almaraz nuclear plant in Extremadura until 8 June 2030, after the nuclear regulator found it could keep running safely; the government kept 2035 as the end date for the whole fleet. Read through Stewart Brand's ecopragmatism, the right approach is to decide each reactor's future on a published test of safety, emissions, cost to consumers and the state of the grid, with owners paying the full cost of waste and Extremadura using the time to build what comes next. Spain's seven reactors still produced 19% of its electricity in 2025.
Key points
- Order TED/864/2026, published on 14 August 2026, lets both Almaraz units run until 8 June 2030, instead of closing in November 2027 and October 2028.
- The Nuclear Safety Council (CSN) issued a favourable report with conditions on 16 July 2026; the minister, Sara Aagesen, says the 2035 horizon for the whole fleet stays.
- The government's own analysis finds the extension lowers renewable output in 2030 by 1.4% against the national plan and gas generation by 7%.
- Nuclear produced 19% of Spain's electricity in 2025 and 47% of Extremadura's, according to Red Eléctrica.
- Five more reactors are due to close between October 2030 and May 2035; each decision should follow a published test of safety, emissions, cost and grid readiness.
On 14 August 2026 the Boletín Oficial del Estado published Order TED/864/2026. It renews the operating licence of the two reactors at Almaraz, on the Tagus in the province of Cáceres, until 8 June 2030 inclusive. Under the schedule agreed in 2019 between the owners and Enresa, the public waste company, unit I was to close on 1 November 2027 and unit II on 31 October 2028. The extension gives them roughly two and a half and one and a half years more.
The path there took nine months. Iberdrola, Endesa and Naturgy, which own about 53%, 36% and 11% of the plant and must agree unanimously, applied on 30 October 2025. pv magazine reported that Iberdrola and Endesa would have liked ten years and Naturgy did not, and the request ended at June 2030, the date the plant's periodic safety review runs to. The Nuclear Safety Council (CSN) asked for more documents in December, the ministry suspended the procedure in February until the regulator reported, and on 16 July 2026 the CSN gave a favourable report with conditions. The order followed four weeks later.
What the order says
The order is worth reading, because its reasoning is more careful than most of the debate. It cites the crisis in the Middle East and the higher, more volatile gas prices that came with it. It reports the ministry's own sensitivity analysis: with Almaraz running to 2030, renewable generation that year would be 1.4% lower than in the national energy and climate plan, and gas-fired generation 7% lower. Spain's EU renewables target is unaffected. Enresa told the ministry the extra waste would be of little significance, with no extra cost to consumers or the state budget. Red Eléctrica, as system operator, said the plant contributes to security of supply, though in a limited way. And the order expects the owners to use the extra years to bring alternative industry and jobs to the area. One of its conditions obliges the operator to guarantee the safety staff planned for 2028 to 2030.
The minister for the ecological transition, Sara Aagesen, defended the decision in September by saying her three conditions had been met: no cost to citizens, nuclear safety and security of supply. She added that the extension sets no precedent and that the horizon for closing the whole fleet stays at 2035. Sumar, the government's coalition partner, rejected it, and environmental groups in Extremadura have opposed it.
The stakes are large. Red Eléctrica's figures for 2025 put nuclear at 19% of Spanish electricity, behind wind at 21.6% and ahead of solar at 18.4%, with gas combined cycles at 16.8%. In Extremadura nuclear was 47% of regional generation. Spain still has seven reactors, about 7,400 MW. After Almaraz, five more are scheduled to close: Ascó I in October 2030, Cofrentes in November 2030, Ascó II in September 2032, Vandellós II in February 2035 and Trillo in May 2035, according to the calendar reported by El Confidencial Digital. Each owner would have to apply for its own extension.
Europe has moved in the meantime. In March 2026 the European Commission published its nuclear illustrative programme, which estimates about €241 billion of investment to 2050 for extending existing reactors and building new large ones, and sees EU nuclear capacity rising from 98 GW in 2025 to about 109 GW in 2050. Nuclear produced 23.3% of the EU's electricity in 2024. The Clean Industrial Deal, launched in February 2025, puts affordable clean energy at the base of Europe's industrial strategy, and Spain's cheap renewables are its strongest card.
An ecopragmatist reading
Stewart Brand, whose Whole Earth Discipline we explain today, would start from results. Every megawatt-hour from a reactor that is already built and safe is a low-carbon megawatt-hour, and the order itself says the extension cuts gas burn. That counts. So does what we know about Spain's grid: renewables and new industry are waiting for connections, curtailment is rising and storage is still small. A reactor that closes before its replacement is connected means more gas in the evening, more emissions and higher prices, which is the outcome both the left and the right say they want to avoid.
The left brings a principle that must stay. The polluter pays: the fee the plants pay to Enresa exists so that waste and dismantling are paid for by those who produce them, and the order's promise of no cost to consumers should be checked and published year by year. The left also speaks for the people of Campo Arañuelo, around the plant, who were facing a cliff in 2027 and are owed a real plan. The market-liberal tradition brings another principle. A plant that the regulator finds safe and that covers its own costs should be allowed to compete, and the tax burden should be set by the cost of waste and safety, never as a tool to push it out early.
Combined, they argue for replacing a calendar fixed in 2019 with a test that is published and applied to each reactor in turn. A reactor keeps running while three things hold: the CSN finds it safe, the owners pay the full cost of waste and decommissioning, and running it lowers emissions and system costs. It closes when the grid, storage and renewable capacity to replace it are connected in the same part of the system, which Red Eléctrica can measure and publish. For Almaraz that means using the years to 2030 to build the lines, batteries and synchronous compensation that Extremadura needs, and to put new industry next to the cheap solar power the region already produces, so that when the reactors stop the jobs and the electricity are already there. For Ascó, Cofrentes, Vandellós and Trillo it means deciding on the same evidence, well ahead of each date.
That is how a radical-centre government would treat nuclear power: as a tool to be judged by its record, kept while it serves the goal and retired when something better is ready.
Questions and answers
When will Almaraz close?
Under Order TED/864/2026, published in the BOE on 14 August 2026, both Almaraz reactors may operate until 8 June 2030 inclusive. The earlier schedule had set closure for unit I on 1 November 2027 and unit II on 31 October 2028.
Why did the Spanish government extend Almaraz?
The order cites higher and more volatile gas prices after the Middle East crisis, a favourable report from the Nuclear Safety Council, a limited contribution to security of supply according to the system operator, and no extra cost to consumers or the state. The minister said the three conditions she had set were met.
How much of Spain's electricity is nuclear?
Red Eléctrica reports that nuclear produced 19% of Spain's electricity in 2025, behind wind at 21.6% and ahead of solar at 18.4%. In Extremadura, where Almaraz is, nuclear was 47% of regional generation.
Is Spain abandoning its nuclear phase-out?
No change to the overall plan has been made. The government says the 2035 horizon for closing all seven reactors remains, and the Almaraz extension sets no precedent. The remaining reactors are scheduled to close between 2030 and 2035, and their owners would have to apply separately for any extension.
Sources
- Orden TED/864/2026, por la que se renueva la autorización de explotación de las unidades I y II de la central nuclear de Almaraz. Boletín Oficial del Estado (2026)
- El CSN avala la prórroga de Almaraz hasta 2030 y traslada la decisión final al Gobierno. pv magazine España (2026)
- Aagesen defiende la prórroga de Almaraz al cumplir los tres requisitos establecidos. EFE / Infobae (2026)
- El sistema eléctrico en Extremadura en 2025 (nota de prensa). Red Eléctrica (2026)
- Almaraz hasta 2030: la decisión que reabre el futuro nuclear. El Confidencial Digital (2026)
- Nuclear investment needs (PINC). European Commission (2026)