Spain's building permits: why a licence takes a year instead of three months, and how to cut it

Spain's legal deadline for a building licence is three months; the real wait is about a year and adds some €13,000 per home. A plan to cut it.

Comic illustration: in the Crane Quarter, Nora lifts a blueprint, Sami strides with a key and Theo points with a magnifier at a stopwatch whose first quarter is shaded gold, while a paper monster of red tape looms behind.

In short

A building licence for new homes in Spain should take three months, but the real average is about 12 months and some projects wait two years, adding roughly €13,000 to each home according to Spain's architects' council. The causes are understaffed councils, overlapping rules, sector reports that arrive late and files still checked almost by hand. The radical-centre fix keeps public control and speeds it up: one digital file, sector reports in parallel with deadlines, staff paid by the licence fee, declarations backed by accredited checks, deemed approval when the council misses the deadline, and published waiting times for every council.

Key points

  • Spanish law recommends a maximum of three months for a licence for major works; the real average for new homes is about 12 months, and some projects wait 18 to 24 months.
  • Spain's architects' council (CSCAE) estimates that 12 months of delay add about €13,000 to the cost of each home.
  • The competition authority CNMC calls for responsible declarations, simultaneous procedures, fewer duplicated approvals and technology to speed up licences and sector reports.
  • The Housing Ministry published a guide with 20 recommendations on licences in December 2025; Portugal's 2024 Simplex reform went further, with tacit approval and online licensing in all 308 municipalities.
  • Speed and control go together when councils have staff, digital files and deadlines that bind.

Spanish law gives a council three months to decide on a licence for a new building. The real wait is about a year. That gap is the most concrete version of the problem Miriam González described in Democracia 21's launch speech on 10 October as a tsunami of paperwork, with almost three years passing before anyone can build. We treat the three-year figure as the party's claim, since it bundles several stages together; the licence stage alone is well measured, and it is bad enough. Our overview of the speech sets it in context.

How long it really takes

El Español put the numbers together in September 2026. The legal reference is three months from application. The national average is around 12 months, four times as long. The Madrid developers' association ASPRIMA puts the Madrid region at 12 to 14 months and says waits of 18 to 24 months happen more often than they should. The construction employers' confederation CNC and the buyers' platform SOMRIE confirmed waits of a year and a half to two years for some residential projects.

The cost lands on the home. The Spanish architects' council, CSCAE, estimates that 12 months of delay add about €13,000 to each home, through building costs, fees, maintenance and finance. ASPRIMA points out that families who have bought off plan keep paying rent while they wait. El Español tells the story of a seven-home project in Blanes, Girona, filed in October 2023 and licensed in July 2025, still missing another authorisation in September 2026, with the buyers' contracts amended twice.

And the licence is only the last step. Our explainer on developable land shows that turning rural land into building plots takes 10 to 15 years, according to the CNMC.

Why it is slow

The people El Español consulted name the same causes: too few technical staff in councils, turnover in municipal teams, reports required from several bodies, municipal, regional and state rules that overlap, and little digitalisation. ASPRIMA says part of the review is still done in an almost handcrafted way. It also warns that thousands of homes in medium-sized towns are about to enter the process, in councils that may not have the capacity to handle them.

The competition authority, CNMC, reached the same diagnosis in its 2026 study on land for housing. The building stage carries multiple controls and administrative requirements, sometimes disproportionate, that can delay licences without justification. Sector rules on environment, water or roads add duplications and blockages, including negative silences, where a missing report counts as a no.

Marc Dunkelman's book Why Nothing Works gives the general pattern a name. Systems designed to restrain power can end up as what he calls a vetocracy, where nearly anyone can stifle progress. A licence queue is vetocracy in its most ordinary form, with no villain at all.

What is already on the table

The CNMC's recommendations are concrete. Remove duplicated or unnecessary steps, such as successive approvals. Promote responsible declarations in place of licences. Run procedures at the same time instead of one after another. Keep requirements on builders proportionate. Use technology to speed up both licences and sector reports.

The Housing Ministry published a guide with 20 recommendations and good practices on residential licences, dated 29 December 2025 and drawn up with the federation of municipalities FEMP and the architects' council. It covers full digital files, coordination between administrations, common criteria and a role for professionals, and it analyses 30 municipalities. It is guidance, so each council decides whether to follow it.

Portugal went further. Its Simplex Urbanístico, Decree-Law 10/2024, moved more works from licences to prior communication, let builders start without the municipal permit document once fees are paid, and introduced tacit approval when the municipality misses its deadline, which runs from 120 to 200 days depending on the project. Since 5 January 2026 an online licensing platform is mandatory in all 308 Portuguese municipalities. Montepio's guide for buyers still advises checking a property's legal status, since a missing licence can complicate a mortgage or a later sale. Spain can borrow the speed and design the safeguards from the start.

The radical-centre plan

From the left we keep public control. Safety, environmental and planning rules exist for good reasons, and the people who check them should be properly staffed public services. From the market-liberal side we take deadlines that bind: if the council does not answer within the legal period, a complete application for homes on land already zoned for them is approved, and responsible declarations replace licences wherever the risk is low. The idea that fits neither camp comes from treating permitting as a delivery service, in the spirit of the delivery approach Jennifer Pahlka argues for: measure it, staff it and fix it from the user's side.

Put together, for a law that Congress and the regions could agree:

  • One digital file per project, shared by the council and every body that has to report, with all sector reports requested on day one and running in parallel, each with its own deadline.
  • Silence counts as yes for new homes on fully planned land, as the Partido Popular's 2026 housing bill proposes for new buildings after three months, with the exceptions for protected buildings and rural land kept.
  • Accredited checkers. Councils can rely on certificates from accredited professional bodies for technical compliance, and keep inspection powers afterwards, with liability insurance for whoever certifies.
  • Fees pay for staff. The licence fee, already capped at cost, funds the technicians who process files, so more applications bring more capacity, as we propose in today's piece on council incentives.
  • Publish the wait. Every council publishes the median time from application to licence each quarter, and the regions compare them.

A licence in three months is the law already. This plan simply makes it the normal experience, with the same checks, done on time.

Questions and answers

How long does a building licence take in Spain?

The recommended legal maximum for major works is three months. The developers' association ASPRIMA puts the real average at about 12 months nationally and 12 to 14 months in the Madrid region, with some projects waiting 18 to 24 months.

Why do building licences take so long in Spain?

Sources consulted by El Español in September 2026 point to a lack of technical staff, changes in municipal teams, reports required from several bodies, overlapping municipal, regional and state rules, and files still reviewed in an almost handcrafted way.

What is a declaración responsable?

A responsible declaration lets the owner start certain works after declaring that they meet the rules, with the council checking afterwards. It already replaces the licence for many minor works, and the CNMC recommends extending it.

What did Democracia 21 say about paperwork?

Miriam González's launch speech on 10 October 2026 described a tsunami of paperwork that means almost three years pass before you can build. We treat that figure as the party's claim; the official data in this article measure the licence stage alone.

Sources

  1. España cuadruplica el plazo legal para conceder licencias de vivienda: la espera encarece cada casa en 13.000 euros. El Español (2026)
  2. Estudio sobre la transformación urbanística del suelo para vivienda: preguntas y respuestas. CNMC (2026)
  3. El Ministerio de Vivienda publica una guía para acelerar las licencias. Brainsre.news (2026)
  4. Simplex urbanístico: o que mudou nas obras e na compra de casa. Montepio (2026)
  5. El Congreso admite a trámite la ley de vivienda del PP con Junts a favor y el Gobierno en contra. Forbes España (2026)
  6. Why Nothing Works (research brief). Watson School, Brown University (2025)